Six budgeting errors that sink commercial projects (and the fixes)

Six budgeting errors that sink commercial projects (and the fixes) photo. Recommended 1600x900.

Halfway through a hotel renovation an owner showed us the spreadsheet he had built eighteen months earlier. The construction number was close. What was missing was everything around it: furniture, signage, the extra months of debt service from a late start, and the contingency he had deleted to make the loan work. The budget was not wrong so much as incomplete. Here are the six gaps we see most often, and what closing each one looks like.

Starting from the wrong number

The first mistake is budgeting from an average. A per-square-foot figure from an article or a friend's project describes someone else's building, finish level and site. It is fine as a first gut check and dangerous as a budget. The fix is to get a trade-by-trade estimate from real drawings, or at least a real program, before the number goes to the lender. Any range we give is a planning range that varies by scope and year, and we say so.

The second mistake is deleting the contingency. Owners treat it as padding and cut it to make the pro forma close. Then a field condition or a late selection shows up, and there is nowhere to put it. A contingency is the honest price of the unknowns every project carries. Keep it in the number and keep it separate from the construction line, so you can see it spent or saved.

Deciding too late

The third mistake is leaving selections open into construction. Every allowance is a decision not yet made, and a decision made under schedule pressure almost always costs more than the same decision made at the start: the lead time forces a substitute, the substitute costs a premium, and the crew waited. We hand owners a decision calendar with the estimate so the finish, fixture and equipment choices close before the trade that installs them is on site.

Forgetting what is not in the building

The fourth mistake is underestimating the site. Soil, drainage, utilities, paving, detention and permitting fees can be a large share of a ground-up budget, and on renovation work the equivalent is existing conditions behind walls and above ceilings. A survey, a soils report and a walk-through with a flashlight before pricing turn those into line items.

The fifth mistake is leaving FF&E outside the construction budget. Casegoods, seating, artwork, signage, kitchen smallwares, fitness equipment and technology are often budgeted separately or not at all, and then someone has to receive, stage and install them in the last three weeks. We install FF&E with our own crews and schedule it inside the job, so the furniture line and the labor to place it are both in the number from day one.

Ignoring the cost of the calendar

The sixth mistake is comparing bids on price and not on date. A lower bid with a longer schedule can cost more once you count extra interest, extended rent on the old location, brand penalties on a PIP deadline, and the revenue the building does not earn while it sits unopened. Put a dollar value on each week of delay and use it when you compare proposals. On our jobs the owner of the company prices the work and runs the site, and the schedule we give you is the schedule that person is accountable for.

A budget that survives the job

A complete budget has a construction number built from real scope, a contingency you can see, a decision calendar that closes the allowances, the site and existing conditions priced from evidence, FF&E inside the plan, and a schedule with a cost attached to slipping it. None of that is complicated. It just has to be done before the loan closes rather than after the crew is on site.

We are licensed and insured. The principals carry over 20 years of combined experience between them, and the person who builds your estimate is the person who will walk your punch list. Send whatever plans you have, even early ones, and we will give you a budget with all six gaps closed.

Email Facebook X LinkedIn

Browse everything we build →

Start your project

← All articles

Start your project